Judgment of the Court (Second Chamber) of 26 March 2015.

Delivered 2015-03-26 · ECLI:EU:C:2015:203 · Court of Justice · Languages: LT · EN · IT · SV · PL · LV · ET · SL · FR · DE

Case
C-596/13
Court
Court of Justice
Date
2015-03-26
Parties
European Commission v Moravia Gas Storage a.s.
ECLI
ECLI:EU:C:2015:203
Original
EUR-Lex ↗
President · rapporteurR. Silva de LapuertaJudgeJ.‑C. BonichotJudgeA. ArabadjievJudgeJ.L. da Cruz VilaçaJudgeC. LycourgosAdvocate GeneralJ. KokottRegistrarA. Calot Escobar
Summary
Preparing…

JUDGMENT OF THE COURT (Second Chamber)

26 March 2015 (*1)

‛Appeals — Internal market in natural gas — Obligation of natural gas undertakings — Organisation of a system of negotiated third party access to gas storage facilities — Decision of the Czech authorities — Temporary exemption for future underground gas storage facilities in Dambořice — Commission decision — Order to withdraw the exemption decision — Directives 2003/55/EC and 2009/73/EC — Temporal application’

In Case C‑596/13 P,

APPEAL under Article 56 of the Statute of the Court of Justice of the European Union, brought on 21 November 2013,

European Commission , represented by L. Armati and K. Herrmann, acting as Agents, with an address for service in Luxembourg,

appellant,

the other parties to the procedure being:

Moravia Gas Storage a.s ., formerly Globula a.s., established in Hodonín (Czech Republic), represented by P. Zákoucký and D. Koláček, advokáti,

applicant at first instance,

Czech Republic , represented by M. Smolek, T. Müller and J. Vláčil, acting as Agents,

intervener at first instance,

THE COURT (Second Chamber),

composed of R. Silva de Lapuerta (Rapporteur), President of the Chamber, J.‑C. Bonichot, A. Arabadjiev, J.L. da Cruz Vilaça and C. Lycourgos, Judges,

Advocate General: J. Kokott,

Registrar: A. Calot Escobar,

having regard to the written procedure,

after hearing the Opinion of the Advocate General at the sitting on 11 December 2014,

gives the following

Judgment

Legal context

‘1. Major new gas infrastructures, i.e. interconnectors between Member States, [liquefied natural gas (LNG)] and storage facilities, may, upon request, be exempted from the provisions of Articles 18, 19, 20, and 25(2), (3) and (4) under the following conditions:

The regulatory authority referred to in Article 25 may, on a case by case basis, decide on the exemption referred to in paragraphs 1 and 2. However, Member States may provide that the regulatory authorities shall submit, for formal decision, to the relevant body in the Member State its opinion on the request for an exemption. This opinion shall be published together with the decision.

The exemption may cover all or parts of, respectively, the new infrastructure, the existing infrastructure with significantly increased capacity or the modification of the existing infrastructure.

In particular, the information shall contain:

Within two months after receiving a notification, the Commission may request that the regulatory authority or the Member State concerned amend or withdraw the decision to grant an exemption. The two month period may be extended by one additional month where additional information is sought by the Commission.

If the regulatory authority or Member State concerned does not comply with the request within a period of four weeks, a final decision shall be taken in accordance with the procedure referred to in Article 30(2).

The Commission shall preserve the confidentiality of commercially sensitive information.’

‘1. Major new gas infrastructure, i.e. interconnectors, LNG and storage facilities, may, upon request, be exempted, for a defined period of time, from the provisions of Articles 9, 32, 33 and 34 and Article 41(6), (8) and (10) under the following conditions:

Where all the regulatory authorities concerned agree on the request for exemption within six months of the date on which it was received by the last of the regulatory authorities, they shall inform the Agency of their decision.

The Agency shall exercise the tasks conferred on the regulatory authorities of the Member States concerned by the present Article:

All regulatory authorities concerned may, jointly, request that the period referred to in point (a) of the third subparagraph is extended by up to three months.

In deciding to grant an exemption, consideration shall be given, on a case-by-case basis, to the need to impose conditions regarding the duration of the exemption and non-discriminatory access to the infrastructure. When deciding on those conditions, account shall, in particular, be taken of the additional capacity to be built or the modification of existing capacity, the time horizon of the project and national circumstances.

Before granting an exemption, the regulatory authority shall decide upon the rules and mechanisms for management and allocation of capacity. The rules shall require that all potential users of the infrastructure are invited to indicate their interest in contracting capacity before capacity allocation in the new infrastructure, including for own use, takes place. The regulatory authority shall require congestion management rules to include the obligation to offer unused capacity on the market, and shall require users of the infrastructure to be entitled to trade their contracted capacities on the secondary market. In its assessment of the criteria referred to in points (a), (b) and (e) of paragraph 1, the regulatory authority shall take into account the results of that capacity allocation procedure.

The exemption decision, including any conditions referred to in the second subparagraph of this paragraph, shall be duly reasoned and published.

Where the requested information is not provided within the period set out in the request, the notification shall be deemed to be withdrawn unless, before the expiry of that period, either the period has been extended with the consent of both the Commission and the regulatory authority, or the regulatory authority, in a duly reasoned statement, has informed the Commission that it considers the notification to be complete.

The regulatory authority shall comply with the Commission decision to amend or withdraw the exemption decision within a period of one month and shall inform the Commission accordingly.

The Commission shall preserve the confidentiality of commercially sensitive information.

The Commission’s approval of an exemption decision shall lose its effect two years from its adoption in the event that construction of the infrastructure has not yet started, and five years from its adoption in the event that the infrastructure has not become operational unless the Commission decides that any delay is due to major obstacles beyond control of the person to whom the exemption has been granted.

Facts of the dispute

Procedure before the General Court and the judgment under appeal

Forms of order sought by the parties

The appeal

Arguments of the parties

Findings of the Court

The action before the General Court

Costs

On those grounds, the Court (Second Chamber) hereby:

[Signatures]

(*1) Language of the case: English.