Judgment of the Court (First Chamber), 28 February 2013.

Delivered 2013-02-28 · ECLI:EU:C:2013:116 · Court of Justice · Languages: LT · EN · IT · SV · PL · LV · ET · SL · FR · DE

Case
C-556/10
Court
Court of Justice
Date
2013-02-28
Parties
European Commission v Federal Republic of Germany
ECLI
ECLI:EU:C:2013:116
Original
EUR-Lex ↗
PresidentA. TizzanoJudge · rapporteurA. Borg BarthetJudgeE. LevitsJudgeJ.-J. KaselJudgeM. BergerAdvocate GeneralN. JääskinenRegistrarC. Strömholm
Summary
Preparing…

Parties

Grounds

Operative part

Parties

In Case C-556/10,

ACTION for failure to fulfil obligations under Article 258 TFEU, brought on 26 November 2010,

European Commission, represented by G. Braun and H. Støvlbæk, acting as Agents, with an address for service in Luxembourg,

applicant,

v

Federal Republic of Germany, represented by T. Henze, J. Möller and N. Graf Vitzthum, acting as Agents, and R. Van der Hout, advocaat,

defendant,

supported by:

Czech Republic, represented by M. Smolek, J. Očková and T. Müller, acting as Agents,

Italian Republic, represented by G. Palmieri, acting as Agent, and S. Fiorentino, avvocato dello Stato, with an address for service in Luxembourg,

interveners,

THE COURT (First Chamber),

composed of A. Tizzano, President of the Chamber, A. Borg Barthet (Rapporteur), E. Levits, J.-J. Kasel and M. Berger, Judges,

Advocate General: N. Jääskinen,

Registrar: C. Strömholm, Administrator,

having regard to the written procedure and further to the hearing on 23 May 2012,

after hearing the Opinion of the Advocate General at the sitting on 6 September 2012,

gives the following

Judgment

Grounds

the German Federal Republic has failed to fulfil its obligations under Article 6(3) of, and Annex II to, Directive 91/440, Articles 4(2) and 14(2) of Directive 2001/14, Articles 6(2), 7(3) and 8(1) of that directive and Article 30(4) of Directive 2001/14 in conjunction with Article 10(7) of Directive 91/440.

Legal context

European Union law

Directive 91/440

‘… the future development and efficient operation of the railway system may be made easier if a distinction is made between the provision of transport services and the operation of infrastructure; … given this situation, it is necessary for these two activities to be separately managed and have separate accounts’.
‘1. Member States shall take the measures necessary to ensure that separate profit and loss accounts and balance sheets are kept and published, on the one hand, for business relating to the provision of transport services by railway undertakings and, on the other, for business relating to the management of railway infrastructure. Public funds paid to one of these two areas of activity may not be transferred to the other.

The accounts for the two areas of activity shall be kept in a way that reflects this prohibition.

Member States may, however, assign to railway undertakings or any other body the collecting of the charges and the responsibility for managing the railway infrastructure, such as investment, maintenance and funding.’

‘Without prejudice to Community and national regulations concerning competition policy and the institutions with responsibility in that area, the regulatory body established pursuant to Article 30 of Directive 2001/14/EC, or any other body enjoying the same degree of independence shall monitor the competition in the rail services markets, including the rail freight transport market.

That body shall be set up in accordance with the rules in Article 30(1) of the said Directive. Any applicant or interested party may lodge a complaint with this body if it feels that it has been treated unjustly, has been the subject of discrimination or has been injured in any other way. On the basis of the complaint and, where appropriate, on its own initiative, the regulatory body shall decide at the earliest opportunity on appropriate measures to correct undesirable developments in these markets. In order to ensure the necessary possibility of judicial control and the requisite cooperation between national regulatory bodies, Article 30(6) and Article 31 of the said Directive shall apply in this context.’

‘– preparation and decision-making related to the licensing of railway undertakings including granting of individual licenses,

Directive 2001/14

‘(12) Within the framework set out by Member States charging and capacity-allocation schemes should encourage railway infrastructure managers to optimise use of their infrastructure.

…

(16) Charging and capacity allocation schemes should allow for fair competition in the provision of railway services.

…

(20) It is desirable to grant some degree of flexibility to infrastructure managers to enable a more efficient use to be made of the infrastructure network.

…

(40) A railway infrastructure is a natural monopoly. It is therefore necessary to provide infrastructure managers with incentives to reduce costs and manage their infrastructure efficiently.

…

(46) The efficient management and fair and non-discriminatory use of rail infrastructure require the establishment of a regulatory body that oversees the application of these Community rules and acts as an appeal body, notwithstanding the possibility of judicial review.’

‘This Directive concerns the principles and procedures to be applied with regard to the setting and charging of railway infrastructure charges and the allocation of railway infrastructure capacity.’
‘1. Member States shall establish a charging framework while respecting the management independence laid down in Article 4 of Directive 91/440/EEC.

Subject to the said condition of management independence, Member States shall also establish specific charging rules or delegate such powers to the infrastructure manager. The determination of the charge for the use of infrastructure and the collection of this charge shall be performed by the infrastructure manager.

‘1. Member States shall lay down conditions, including where appropriate advance payments, to ensure that, under normal business conditions and over a reasonable time period, the accounts of an infrastructure manager shall at least balance income from infrastructure charges, surpluses from other commercial activities and State funding on the one hand, and infrastructure expenditure on the other.

Without prejudice to the possible long-term aim of user cover of infrastructure costs for all modes of transport on the basis of fair, non-discriminatory competition between the various modes, where rail transport is able to compete with other modes of transport, within the charging framework of Articles 7 and 8, a Member State may require the infrastructure manager to balance his accounts without State funding.

…

‘3. Without prejudice to paragraphs 4 or 5 or to Article 8, the charges for the minimum access package and track access to service facilities shall be set at the cost that is directly incurred as a result of operating the train service.
‘1. In order to obtain full recovery of the costs incurred by the infrastructure manager a Member State may, if the market can bear this, levy mark-ups on the basis of efficient, transparent and non-discriminatory principles, while guaranteeing optimum competitiveness in particular of international rail freight. The charging system shall respect the productivity increases achieved by railway undertakings.

The level of charges must not, however, exclude the use of infrastructure by market segments which can pay at least the cost that is directly incurred as a result of operating the railway service, plus a rate of return which the market can bear.

‘Without prejudice to Articles 81, 82, 86 and 87 of the Treaty and notwithstanding Article 7(3) of this Directive, any discount on the charges levied on a railway undertaking by the infrastructure manager, for any service, shall comply with the criteria set ou t in this Article.’
‘1. Member States may establish a framework for the allocation of infrastructure capacity while respecting the management independence laid down in Article 4 of Directive 91/440/EEC. Specific capacity allocation rules shall be established. The infrastructure manager shall perform the capacity allocation processes. In particular, the infrastructure manager shall ensure that infrastructure capacity is allocated on a fair and non-discriminatory basis and in accordance with Community law.
‘1. … Member States shall establish a regulatory body. … The body shall function according to the principles outlined in this Article whereby appeal and regulatory functions may be attributed to separate bodies.

…

Notwithstanding paragraph 6, a decision of the regulatory body shall be binding on all parties covered by that decision.

…’

German law

‘In the exercise of their functions, the railway supervisory authorities may take, in respect of those bound by the provisions cited in Paragraph 5(1), the measures necessary in order to deal with infringements that are established and to prevent future infringements of the provisions referred to in Paragraph 5(1).’
‘(1) Public railway managers must be independent of all rail transport undertakings in their legal form, organisation and decision making where the decisions at issue concern path allocation and charging. In order to attain the objectives set out in the first sentence, it is necessary:
‘Railway managers must set their charges in accordance with an order adopted under points 6 and 7 of Paragraph 26(1) in such a way as to offset the costs they incur in order to provide statutory services within the meaning of the first sentence of Paragraph 26(1), plus a rate of return which the market can bear. In doing so they may levy mark-ups on the cost that is directly incurred as a result of operating the rail service, and may distinguish between long-distance passenger services, short-distance passenger services and rail freight services, and also between market segments within those services, while guaranteeing competitiveness, in particular of international rail freight. The level of charges shall not, however, under the second sentence of Paragraph 26(1), exceed, in respect of any particular market segment, the cost that is directly incurred as a result of operating the rail service, plus a rate of return which the market can bear. In the order adopted under points 6 and 7 of Paragraph 26(1):
‘(1) In the exercise of its functions, the regulatory body shall take, in respect of public railway infrastructure undertakings, the measures necessary in order to deal with infringements that are established and to prevent future infringements of the provisions of railway legislation concerning access to railway infrastructure.

(2) Entities authorised to have access to the infrastructure, public railway infrastructure undertakings and their staff must allow the regulatory body and its representatives, in the performance of their tasks:

(3) Entities authorised to have access to infrastructure, public railway infrastructure undertakings and their staff must provide the regulatory body and its representatives with:

This provision shall apply also to talks, in progress or ended, concerning the amount of charges for infrastructure use and other charges. The information supplied must be correct and prepared in good faith. Any person required to supply information may refuse to answer questions where the answer would expose him, or one of the persons described in points 1 to 3 of Paragraph 383(1) of the Code of Civil Procedure, to the risk of criminal prosecution or proceedings for an administrative offence.

(4) Under the present law, the regulatory body may enforce its orders in accordance with the provisions governing the enforcement of administrative measures. The penalty payment may amount to EUR 500 000.’

‘No derogation shall be made from the principle of the legal and organisational independence of [DB Netz] with regard to decisions concerning the working timetable, path allocation and charging. [DB AG] shall not give any instruction jeopardising that principle.’

‘…

The pre-litigation procedure and the procedure before the Court

The action

The complaint concerning the independence of the body entrusted with the exercise of essential functions listed in Annex II to Directive 91/440

Arguments of the parties

Findings of the Court

The complaint relating to charging

Arguments of the parties

Findings of the Court

The complaint relating to incentives to reduce costs

Arguments of the parties

Findings of the Court

The complaint relating to the powers of the regulatory body

Arguments of the parties

Findings of the Court

Costs

Operative part

On those grounds, the Court (First Chamber) hereby:

Text from our archive (Publications Office of the EU, Cellar). Commission Decision 2011/833/EU — free reuse incl. commercial; attribution to EUR-Lex / Court of Justice of the European Union required; EUR-Lex is not the authentic record of the Court.