Failure of a Member State to fulfil obligations – Failure to comply with Article 2 of Commission Decision of 26 September 2006 (Case No COMP/M.4197 – E.ON/Endesa – C(2006) 4279 final) and Article 2 of Commission Decision of 20 December 2006 (Case No COMP/M.4197 – E.ON/Endesa – C(2006) 7039 final).
Operative part
Operative part
The Court:
1) declares that by not withdrawing:
the conditions 1 to 6, 8 and 17 imposed by the decision of the National Energy Committee which were declared incompatible with Community law by Article 1 of the Commission Decision of 26 September 2006 (Case No COMP/M.4197 – E.ON/Endesa – C(2006) 4279 final), and
conditions 1, 10, 11 and 15, as amended, imposed by decision of the Ministry of Industry, Tourism and Trade which were declared incompatible with Community law by Article 1 of the Commission Decision of 20 December 2006 (Case No COMP/M.4197 – E.ON/Endesa – C(2006) 7039 final), the Kingdom of Spain has failed to fulfil its obligations under Article 2 of each of those decisions;
2) Orders the Kingdom of Spain to pay the costs .
Text from our archive (Publications Office of the EU, Cellar). Commission Decision 2011/833/EU — free reuse incl. commercial; attribution to EUR-Lex / Court of Justice of the European Union required; EUR-Lex is not the authentic record of the Court.