Judgment of the Court (Fourth Chamber) of 10 April 2008.

Delivered 2008-04-10 · ECLI:EU:C:2008:213 · Court of Justice · Languages: LT · EN · IT · SV · PL · LV · ET · SL · FR · DE

Case
C-393/06
Court
Court of Justice
Date
2008-04-10
Parties
Ing. Aigner, Wasser-Wärme-Umwelt, GmbH v Fernwärme Wien GmbH.
ECLI
ECLI:EU:C:2008:213
Original
EUR-Lex ↗
PresidentK. LenaertsJudgeG. ArestisJudge · rapporteurE. JuhászJudgeJ. MalenovskýJudgeT. von DanwitzAdvocate GeneralD. Ruiz-Jarabo ColomerRegistrarB. Fülöp
Summary
Preparing…

Parties

Grounds

Operative part

Parties

In Case C‑393/06,

REFERENCE for a preliminary ruling under Article 234 EC, from the Vergabekontrollsenat des Landes Wien (Austria), made by decision of 17 August 2006, received at the Court on 22 September 2006, in the proceedings

Ing. Aigner, Wasser-Wärme-Umwelt GmbH

v

Fernwärme Wien GmbH,

THE COURT (Fourth Chamber),

composed of K. Lenaerts, President of the Chamber, G. Arestis, E. Juhász (Rapporteur), J. Malenovský and T. von Danwitz, Judges,

Advocate General: D. Ruiz-Jarabo Colomer,

Registrar: B. Fülöp, Administrator,

having regard to the written procedure and further to the hearing on 11 October 2007,

after considering the observations submitted on behalf of:

Judgment

Grounds

Legal context

Community legislation

‘… any body:

financed, for the most part, by the State, regional or local authorities, or other bodies governed by public law; or subject to management supervision by those bodies; or having an administrative, managerial or supervisory board, more than half of whose members are appointed by the State, regional or local authorities, or by other bodies governed by public law’.

‘For the purposes of this Directive,

…

(b) a “public undertaking” is any undertaking over which the contracting authorities may exercise directly or indirectly a dominant influence by virtue of their ownership of it, their financial participation therein, or the rules which govern it.’

‘This Directive shall apply to contracting entities:

(a) which are contracting authorities or public undertakings and which pursue one of the activities referred to in Articles 3 to 7;

(b) which, when they are not contracting authorities or public undertakings, have as one of their activities any of the activities referred to in Articles 3 to 7, or any combination thereof and operate on the basis of special or exclusive rights granted by a competent authority of a Member State.’

‘As far as gas and heat are concerned, this Directive shall apply to the following activities:

(a) the provision or operation of fixed networks intended to provide a service to the public in connection with the production, transport or distribution of gas or heat; or

(b) the supply of gas or heat to such networks.’

‘1. A contract which is intended to cover several activities shall be subject to the rules applicable to the activity for which it is principally intended.

However, the choice between awarding a single contract and awarding a number of separate contracts may not be made with the objective of excluding it from the scope of this Directive or, where applicable, Directive 2004/18/EC.

…’

‘This Directive shall not apply to contracts which the contracting entities award for purposes other than the pursuit of their activities as described in Articles 3 to 7 or for the pursuit of such activities in a third country, in conditions not involving the physical use of a network or geographical area within the Community.’
‘1. Contracts intended to enable an activity mentioned in Articles 3 to 7 to be carried out shall not be subject to this Directive if, in the Member State in which it is performed, the activity is directly exposed to competition on markets to which access is not restricted.

…’

‘This Directive shall not apply to public contracts which, under Directive 2004/17/EC, are awarded by contracting authorities exercising one or more of the activities referred to in Articles 3 to 7 of that Directive and are awarded for the pursuit of those activities, …

…’

The dispute in the main proceedings and the questions referred for a preliminary ruling

‘1. Must Directive 2004/17 … be interpreted as meaning that a contracting entity which pursues one of the sectoral activities referred to in Article 3 of that directive also falls within the scope of that directive in relation to an activity pursued in parallel under competitive conditions?

The questions referred for a preliminary ruling

The first question

The second question

The third question

Costs

Operative part

On those grounds, the Court (Fourth Chamber) hereby rules: