Judgment of the Court (First Chamber) of 21 June 2007.

Delivered 2007-06-21 · ECLI:EU:C:2007:370 · Court of Justice · Languages: LT · EN · IT · SV · PL · LV · ET · SL · FR · DE

Case
C-158/06
Court
Court of Justice
Date
2007-06-21
Parties
Stichting ROM-projecten v Staatssecretaris van Economische Zaken.
ECLI
ECLI:EU:C:2007:370
Original
EUR-Lex ↗
JudgeR. SchintgenJudgeA. TizzanoJudgeA. Borg BarthetJudge · rapporteurM. IlešičJudgeE. LevitsJudgePrincipal AdministratorAdvocate GeneralJ. MazákRegistrarM. Ferreira
Summary
Preparing…

Parties

Grounds

Operative part

Parties

In Case C‑158/06,

REFERENCE for a preliminary ruling under Article 234 EC, by the College van Beroep voor het bedrijfsleven, made by decision of 16 March 2006, received at the Court on 23 March 2006, in the proceedings

Stichting ROM-projecten

v

Staatssecretaris van Economische Zaken

THE COURT (First Chamber),

composed of R. Schintgen, President of the Fifth Chamber, acting for the President of the First Chamber, A. Tizzano, A. Borg Barthet, M. Ilešič (Rapporteur) and E. Levits, Judges,

Advocate General: J. Mazák,

Registrar: M. Ferreira, Principal Administrator,

having regard to the written procedure and further to the hearing on 1 February 2007,

after considering the observations submitted on behalf of:

Judgment

Grounds

Legal context

‘ Article 1

The SME operational programme for the Netherlands adopted in respect of the period from 30 November 1994 to 31 December 1999 and set out in the annexes below, which encompasses a coherent set of multiannual measures within the framework of the SME Community initiative for the benefit of areas eligible under Objectives 1 and 2 in the Netherlands, is hereby approved.

…

Article 6

The Community assistance concerns expenditure on operations under this programme which, in the Member State concerned, are the subject of legally binding commitments and for which the requisite finance has been specifically allocated no later than 31 December 1999. The final date for taking account of expenditure on these measures is 31 December 2001.

…

Article 9

This Decision is addressed to the Kingdom of the Netherlands.’

The dispute in the main proceedings and the questions referred for a preliminary ruling

‘(1) Is Article 6 of the … [grant decision] unconditional and sufficiently precise to be directly applicable in the national legal order?

(2) If the answer to Question 1 is in the affirmative: Must Article 249 EC be interpreted as meaning that Article 6 of that decision directly required an individual, as the ultimate beneficiary, to enter into the legally binding commitments referred to in that respect and to specifically allocate the requisite finance no later than 31 December 1999?

(3) If the answer to Question 2 is in the affirmative: Does [the obligation of the Member States to take all necessary measures to recover any amounts lost as a result of an irregularity], viewed in the light of the principles of Community law, leave the Member States discretion to refrain from recovery on account of an infringement of a provision where the beneficiary of the subsidy was unaware of that provision and is not at fault for its lack of knowledge of that provision?’

The questions referred for a preliminary ruling

Initial considerations

‘Where the conditions for the grant of financial assistance by the Community to a Member State are set out in the grant decision but that Member State has neither published them nor made them known to the ultimate beneficiary of the assistance, is it contrary to Community law to apply the principle of legal certainty so as to preclude repayment by that beneficiary of amounts wrongly paid?’

The third question

Observations submitted to the Court

The Court’s answer

The first and second questions

Costs

Operative part

On those grounds, the Court (First Chamber) hereby rules:

Where the conditions for the grant of a financial assistance by the Community to a Member State are set out in the grant decision but that Member State has neither published them nor made them known to the ultimate beneficiary of the assistance, it is not contrary to Community law to apply the principle of legal certainty so as to preclude repayment by that beneficiary of the amounts wrongly paid, provided that it is possible to establish the beneficiary’s good faith. In such a case, the Member State concerned may be held financially liable for the amounts not recovered in order to give effect to the Community’s right to obtain repayment of the amount of the assistance.

Text from our archive (Publications Office of the EU, Cellar). Commission Decision 2011/833/EU — free reuse incl. commercial; attribution to EUR-Lex / Court of Justice of the European Union required; EUR-Lex is not the authentic record of the Court.